Lillie Square Phase 2 | Wates
£145M
Value
186
No. of apartments
91 weeks
Duration

Project overview

Four linked new build 8 storey blocks of high quality apartments and penthouses for private sale.

The complex site had a vast podium slab pre-completed for the five phases. Network rail lines tight to the site required extensive pre-construction engagement. Wates employed a strategy of high pre-fabrication (including riser modules, bathroom pods, unitised cladding) to gain quality and programme benefit, plus strong client team collaboration added early works for subsequent phases.

FIND OUT MORE ABOUT WATES CONSTRUCTION
Lillie Square Phase 2

 