Arnold Hill Secondary School - Wates Construction Case Study

Arnold Hill Academy Nottingham

Construction

60 weeks

Client

DfE

Partner

IID Architects

Construction of Arnold Hill, a new 1,700 place, 3-storey academy on a live logistically-challenging site to replace an existing, structurally compromised 1950s era Upper School building, associated refurbishment to Lower School areas and extensive landscaping.

  • £14.3m Value
  • 60 weeks Build
  • DfE Framework Procurement

Live Environment Logistics

We worked closely with the Academy to carefully manage site logistics and the health and safety/access and daily movement of 2,000 pupils and staff into and across the site.

  • 98.6% Percentage waste diverted from landfill
  • £30k SE spend against target of £15k
  • 5 Apprenticeships supported

We’re absolutely delighted with the job Wates have done. The building has been finished bang on schedule and it’s attracting a lot of positive attention in construction and education circles.”

Lee Roberts Facilities Manager, Arnold Hill