Project overview

Part of the Earl’s Court regeneration, these new-build apartments and penthouses used Wates’ offsite manufacturing facility, Prism, to manufacture all service risers and service cupboards, guaranteeing a high quality of product, and 3D sequencing to improve our control of the programme.

FIND OUT MORE ABOUT WATES CONSTRUCTION
Lillie Square Development

Close collaboration with the customer’s project team also added an early works contract for subsequent phases, whilst a thorough design investigation during the pre-construction services agreement period resulted in the fan cooling units being redesigned, avoiding delays on site. The use of 3D sequencing for the build process resulted in a more seamless installation of the various prefabricated elements within the apartments.

  • 10,000 hours of work taken offsite
  • Just three days to install risers