Gledhow and Castleton Primary Schools | Wates
£9.75m
Value
66 weeks
Duration

Gledhow and Castleton Primary Schools

Project overview

The Leeds Primaries contract comprised of a refurbishment and extension of Gledhow Primary School and the refurbishment, extension and a complete new build of a Children’s Centre at Castleton Primary School.

Works commenced at Gledhow Primary School in March 2016, completing in December 2016, ahead of schedule.

FIND OUT MORE ABOUT WATES CONSTRUCTION
Castledown primary school, leeds

Castleton’s Children’s Centre commenced in May 2016 and was also handed over in December 2016, at which point the refurbishment and extension commenced and was handed over early in August 2017.

Key Features

  • New Build
  • Refurb
  • Education YORbuild
  • BREEAM Very Good
  • 3D Design in Revit
  • 12,500m2