Above all, it's about people

Powergate Phase 1, Telecity Group Plc

Safe, Secure & Efficient – another mission critical data centre build

As the leading pan European provider of network independent data centres Telecity was looking for technical expertise and cost and programme certainty when it embarked on its largest and most complex centre located in North London. A ‘one-solution’ approach meant Wates Technology worked seamlessly to create the 5000m2 of space containing more than £7m of plant. The M&E installation included UPS and generator lacked electrical systems with the main halls providing high density capability cooling by a forced air down flow system along with gas suppression and fire detection.

The Tier 3+ system was introduced in three sections providing 8 data halls. Over 200,000 accident free man hours was achieved on site.

Client: Telecity Group PlC

Project: New Build extension and technical fit out of Tier 3+ data centre.

Duration: 48 weeks

Value: £30m

Categories: data centres, london & south east

Tags: M&E

Christine Baltas
Profile
Business Development Manager
call now on 020 7654 6809

You may filter which project stories you are viewing by using the boxes below. Once you have selected the appropriate boxes, press "search"

show me:

businesses

wates construction
wates living space
wates retail
wates interiors
wates developments

sectors

public sector
education
technology
affordable housing
residential
commercial
retail
land
fit-out
hotels and leisure

other

clear

popular tags

related project stories

thought leadership

latest news