LogicaCMG
Waterton Service Centre

Client: LogicaCMG
Architects: Powell Dobson Partnership
Quantity Surveyor: Davis Langdon
Services Engineer: Hoare Lea
Value: £8m
Project Period: 48 Weeks
Procurement: Two Stage Traditional

 

Interior of LogicaCMG - Waterton Service CentreTransforming a run down, 1970s distribution warehouse into a 60,000sq.ft of Data and Call Centre with associated Mail and Print and Document Handling facilities, within tight, business driven timescales, procured on a two stage basis was the task passed to Wates Interiors by LogicaCMG.

The fit-out of the first 15,000sq.ft of the phased occupation was completed within 5 weeks to meet the business needs of LogicaCMG’s expanding outsourcing business. The remainder of the works to the 250 person call centre and another 15,000sq.ft to form a data centre were completed in 15 and 12 weeks respectively.

Call centre at LogicaCMG - Waterton Service CentreOn site, as the design and construction progressed through the project we tailored solutions to meet the customer’s requirements. Constructing the data centre adjacent to a busy call centre operating 24/7 was just one of the challenges overcome by consistent delivery to agreed sequencing of noisy and disruptive work, open and honest dialogue and transparent delivery of our promises.

Making Waterton a successful Operational Support Centre for LogicaCMG, both during the phased fit-out and after completion lay not only with the quality of the installation, but also how the services that provide the support work. Designed and constructed to N+1 resilience the Data Centre is the backbone of the operation that supports the Call Centre, Document Handling and Mail and Print.